Skip Navigation LinksHome > Discussion Papers > 6 BIM in Construction
Skip Navigation Links
HomeExpand Home
 

Transforming Construction?

6.0 Conventional Construction Management

In the construction phase, the absence of data problem arises mainly in regard to project management or project control activities: planning and scheduling and cost control and related functions. The main problem here is with poor forecasting, giving rise to unpredictable cost and schedule outcomes. Project forecasts fail for two broad reasons: because the wrong targets are set at the outset; and because progress is assessed incorrectly during the course of the work. The way in which these and related problems arise can be illustrated by focusing on their effects on project planning.

6.0.1 Problems with Planning.

The conventional planning function involves the creation of activity based project models, generally in the form of CPM networks and Gantt charts. These models have two main purposes: initially to demonstrate that the project at hand is physically / logically achievable; and subsequently, during the course of the work, to provide short-term guidance to action, in the form of look-ahead schedules and such like. But activity models are flawed in both of these areas of use, as the following will make clear.

6.0.2 Subjectivity

Activity planning models are highly subjective creations. On a given project the particular activities chosen, the way in which these activities are defined or specified and the logic links used to connect them are all determined by the personal experience and intuition of the individual planner or project manager. There is nothing standardised or systematic about the activities. In a sense, an activity means what the planner wants it to mean. This has three highly undesirable consequences:

First, the sense or scope of a given activity tends to be cryptic, difficult for other people to comprehend and therefore difficult to challenge or verify independently. This undermines the model's value as a test of the viability of the project. It also has adverse consequences for the model's subsequent use as a management control tool.

Second, the meaning of the activity is not determined and fixed. It can be changed by the planner through the duration of the project. This means that analyses and supposedly like for like comparisons between different points in time on the project can be misleading.

Third, activities tend to very project specific, reflecting the individual planner's personal response to the project at hand. This means that there is little scope for cross project comparison or analysis which, again, makes it very difficult for people other than the planner and his project manager to challenge the plan.

Also as a result of the unsystematic way in which they are used to represent the scope of work of the project, it can often be difficult to carry out progress assessments on a consistent, like for like basis using activity models. There is often a tendency towards optimism bias and other assessment errors which tend to obscure the true situation. This makes performance trends difficult to spot and effective responses hard to devise.

6.0.3 Planning versus Forecasting

It's important to distinguish between plans and forecasts. Once a given project gets under way, the main requirement of the plan is to provide guidance to action: rolling wave look-ahead programmes, short term activity schedules and suchlike. To do this effectively, the plan must reflect accurately the current, real world situation. It must therefore be revised more or less continuously to embody the effects of new information and changing circumstances. The only way this can be done is by re-defining, or re-specifying the activities that make up the model, or by re-arranging the logic links between activities.

Once this starts to happen, like-for-like comparison of the model at different points in time becomes impossible, and the ability to generate consistent long term forecasts is lost. For this reason in particular, planning models make inherently poor forecasting tools. The planning model cannot, logically, be both a short term guide to action and a reliable tool for consistent longer term forecasting.

6.0.4 The Top Down Problem

Conventional project management systems are essentially top down in their structure and operation. It is extremely difficult to integrate them closely with the detail of operations at the production level of the project. This places an great deal of reliance on the front line supervisor to act as the interface, the interpreter, between the planning system and operations on the ground. For the most part individual supervisors can be relied upon reasonably well to understand the plan and to translate its contents into detailed task schedules.

However, when assessing and reporting progress achieved, even the most competent and most experienced supervisors are sometimes betrayed by what academics describe as Optimism Bias. This has been defined as: "a cognitive predisposition found with most people to judge future events in a more positive light than is warranted by actual experience." In the present context it refers to the intuitive reluctance of people to convey bad news to their superiors; instead they delay acknowledging poor progress, often until it's too late to correct. And this happens all the way along the reporting line, from site level right up to the Main Board.

This reporting problem applies to all project management disciplines and is evident at all management levels in project organisations. Everyone involved interprets the information he's given subjectively - because there is no systematic, objective content - and adds his own twist to the story he receives, before passing it on. Sometimes the twist is slight, sometimes it can be critical. Insofar as it substitutes opinion for fact, it's always undesirable.

6.0.5 Responsiveness

Projects very rarely fail catastrophically, completely without warning. There is almost always a history, some process or sequence of developments that leads up to apparently sudden crises. The problem is that planning systems are simply not designed to capture the sort of historical information that might be useful in detecting these sequences or trends.

They capture reasonably well the "instant in time" snapshot pictures, cross-sections through the history of the project that are necessary for short term activity planning. But these systems are very poor at knitting these cross-sections together or in other ways producing longitudinal time based views of the project's evolution. Planning systems simply don't cope with trends very well. So project teams often don't realise they are off target until too late and it becomes costly and disruptive to institute corrective actions: "crash" recovery programmes and suchlike.

6.0.6 Learning

The four problems outlined above relate to the difficulty of using planning systems to predict project cost and schedule outcomes, while the project is under way. The fifth problem is more to do with accurately establishing those targets in the first place. It relates to the way in which firms gather and use actual performance data from their projects.

The individual people who work on projects learn a great deal from every job they do. The companies they work for learn almost nothing. The human learning is, for the most part, experiential and unstructured. Companies are not able to 'learn' in that sense. Companies learn by gathering structured data that can be analysed, evaluated and reused in future activities. In order to capture this material the data has to be specified systematically and there must exist organising frameworks or other mechanisms that enable it to be gathered and arranged efficiently for future use. CPM based planning systems meet neither of these conditions: the data used are too subjective and the activity models are too job-specific to be systematically useful on future projects.

6.0.7 Project Management Summary

The issues above have been elaborated upon because they are rarely, if ever, drawn out in discussions of project failure - despite the fact that unless the problems they represent are solved, other attempts to improve construction project predictability will almost certainly fail.

To summarise, our theory suggests that projects fail because conventional project management methods and systems:

  • Depend too much on intuitive, subjective definition of work scope and progress assessment
  • Are dangerously top-down in their operation, lacking systematic connection with the production level in projects
  • Are inherently poor for forecasting and for trend detection and analysis
  • Provide no effective frameworks or methods for the capture, analysis and reuse of performance data.

Similar problems occur in the area of cost control. Again, the principal problem is that the project scope is not specified systematically or in useful detail. Cost models based on Cost Planning techniques - elemental costs per square metre for example - suffer from the same inherent problem of subjective definition as activity models, with the same results.

Bills of Quantities (BQ) at least have the merit of being based on the detail of more or less complete design documentation. However, as discussed at Section 5 above, in order to make a BQ manageable as a paper document, most of the useful information recorded in its development has to be compressed out of the final product. Hundreds of lines of valuable, specific data about individual concrete columns for example, may in some cases be reduced to three or four highly summarised line items in the bill. This is an extraordinary waste of valuable information as well as being a source of ongoing dispute amongst the members of the greater project team.

There are other areas where conventional Planning and Cost Control techniques fail, for the same general reason. Thus, in the absence of a well specified, shared baseline work scope, it is impossible to establish a direct or useful correspondence between cost and planning systems. So the cost and schedule dimensions of the project get out of sync, tell different stories, provide different feed-back to management, generally adding confusion to the picture.

Also, in the absence of a common specification of the scope of the project, it is more or less impossible to carry out useful analyses of the joint cost and schedule impacts of change proposals or other issues. One could go on...

The point is that any given construction project manager, starting out on a new project, equipped with all the technologies and management tools the modern industry has to offer, faces a less than 50/50 probability of success. The strong likelihood is that, for all the stress and anxiety that he - and all the other managers on the job - will endure, he will still fail to deliver the thing on time or within budget.

So, what can BIM do to improve this situation. Specifically, how can BIM help teams to deliver their projects more predictability?

6.1 BIM-based Construction Project Management

BIM models will assist in construction in two main ways. The first of these involves simply using the graphical power of sophisticated 3D models as a means of visualising how the building fits together. This includes clash detection and construction simulation exercises, as well as cutting special views of parts of the building to assist in particular construction tasks. This is not strictly using the Information component of BIM models, but is likely to be the application area that drives the use of BIM onto the construction site. A more fundamental application of BIM, in the full sense, lies in its use as a tool for managing production on construction sites. This section discusses the background issues, the motivation for its use and the probable mode of operation of BIM for this purpose.

6.1.1 The Construction Site as a Production Environment.

In an orderly production environment the most reliable way of forecasting how long a given process has to run, at any given point in time, is by taking the total amount of material to be produced, subtracting the amount already produced and dividing the balance by the rate of production achieved to date. The main issues that affect the accuracy of the forecast will be the accuracy with which the variables: total output, output achieved to date, and average rate of production are known. This is the essence of the production management concept.

Two observations indicate that it may be valid to apply this approach to construction. First, although it may not appear obvious, the buzz of commotion on a typical construction site in fact represents a great deal of highly ordered, systematic activity. The work tasks are being carried out by experienced, specialist operatives employed by a variety of specialist contracting firms. For each of these individuals and firms the task at hand is just like every other job they do. The particular configuration of the building, its location, and the other people working on the project are different, but the basic specialist operations being carried out are identical from project to project. In a sense, that's what specialisation is all about.

Secondly, although again it may not seem obvious, buildings are in fact highly standardised things - if one considers them at the level of the individual components that make them up. At the component level, the construction and fabric of apparently different buildings are actually very similar. Almost by law, a steel beam in one building that conforms to BS 4360, is identical to a beam of the same specification in any other building. Similarly with pipework, doors, concrete or any other component; if it's described by a British Standard or an ISO standard, it's essentially the same thing regardless of the particular building in which it occurs. In this sense all modern buildings can be considered as being simply massive aggregations of standard entities. The buildings at the aggregated level may be unique; the components of which they comprise are completely standardised.

So, the construction industry is made up of large numbers of people and firms who, essentially, do the same things, to the same things, on every project they work on. There may be a lot of distracting 'noise' in the system - weather, ground conditions, congestion and such like - but most of the activity on a typical construction site is actually highly systematic, generating standardised outputs in a methodical, repetitive fashion. This implies strongly that the construction site can reasonably be regarded as being an orderly production environment and that it is therefore appropriate to use production management techniques to control operations at this level on projects.

The production management approach overcomes all four of the problems with project management discussed above:

  • It eliminates dependence on intuitive, subjective definition of work scope and progress assessment.
  • It connects management directly to the work face.
  • It enables dramatically improved forecasting and trend monitoring.
  • It provides a comprehensive framework within which to gather, analyse and re-deploy performance data from one project to the next.

The problem with production management is that the sheer volume of information generated at the production level on construction projects is enormous. It requires that a record is made every time a steel fixer bolts up a beam, a carpenter installs a door set, or a plumber installs a spool of pipe. For every event like this a small packet of data has to be captured to record the relevant details. In the case of the steel beam this data might include: the piece number of the beam, the fixer's team identifier, the location in the building and the date and time.


Optimism bias and a related behaviour, strategic misrepresentation, are two problems with estimating and forecasting, much studied by Bent Flyvjberg. See Bent Flyvjberg, Nils Bruzelius and Werner Rothengatter.Megaprojects and Risk: An Anatomy of Ambition. (Cambridge University Press, 2003)

Maureen Platform