Skip Navigation LinksHome > Our Products > Insight™Production Management
Skip Navigation Links
HomeExpand Home
 

Production Management

Conventional, CPM based project management deals mainly with the activities that need to be carried out in order to complete a given project. Production management deals with the physical output generated by those activities.

Thus, an activity plan shows the activities that will be under way, day by day or week by week during the project. A production plan shows the level of physical output that must be generated day by day or week by week throughout the project in order to complete the job on time.

Click to view in Acrobat 

The C3 Production Management project process is illustrated in the diagram above. In broad terms, it works as follows:

  • The starting point for the production plan is a detailed list of the components of the building in question, taken off from the drawings in the form of a 'smart' bill of quantities. Each component is identified according to a catalogue of Unique Component Codes and its location and quantity are recorded.
  • Each component or group of components is then allocated to one or more construction packages. The man-hours and / or monetary cost of installing each component are assigned according to the package schedule of rates. In this way the 'planned value' of each installed component, thus of the package as a whole, is established - before construction gets under way.
  • The key point about this step is that it establishes the 'value' of all the various components of the building in common units: man-hours or monetary cost. This is the basis on which all subsequent calculations are carried out. Reducing everything to a common basis of value enables comparison and aggregation of completely different types of operation, brickwork pipework for example, over time on any given project, and importantly across different projects.
  • The Planned Progress curve for the package in question is generated by spreading the man-hours or costs across the package, or sub-package, duration according to a simple production function.
  • When work gets under way the actual installation of individual components is recorded, as it happens, preferably on a continuous, daily basis. Every time the contractor completes the installation of a component he 'earns' the man-hour or monetary value of that component.
  • This information is added to the production plan generate the 'Earned value' of the work performed. The actual percent complete of the package can then be calculated as the ratio of the earned value to the initial total planned man-hour or monetary value of the package. This is plotted as the Actual Progress curve. Packages can be grouped and totalled in the same way to give group and overall project values and curves.
  • It is highly desirable that when the fact of a component installation is recorded, the man-hours used in its installation are also noted. This enables labour usage, productivity and effectiveness to be monitored and managed.

In general the information required to drive Production Management is neither new nor particularly different. 'Dumb bills of quantities have been in use in construction for over a century. However, as paper documents they lack detail, flexibility and authority. A 'smart' bill retains all of the detail of the building at the most detailed component item level; it's flexible in that it can be used for many purposes other than just tendering and valuation and it's authoritative in that every item it contains can be challenged explicitly, can thus be verified definitively.

The progress information used in production management is a simple extract from the trade supervisor's daily diary. The man-hour usage information can be obtained from the same source or from the specialist contractor's time recording system. Obviously, the Production Management system can be used to generate turnaround documents for the capture of this information or to drive hand held data capture devices or similar.

 

Yorkhill Hospital, Glasgow